Hornsea Project One - The first load-out

The first load-out of the first 6 transition pieces and anode cages ...

28 February 2018

The loadout of the first 6 transition pieces and anode cages for Hornsea Project One offshore wind farm took place last week at our facilities in Aalborg and everything went according to plan.

In total Bladt Industries will deliver 124 transition pieces and anode cages for the Ørsted project – Hornsea Project One.

The last loadout of the transition pieces for the project is expected to take place in Q3 2018. 

Bladt Industries are also working on the three substations and Reactive Compensation Station for Hornsea Project One.

Hornsea Project One will become the biggest windfarm in the world, with a total capacity of 1.2 GW and span an area of 407 km2.