Expanding our capacity for Transition Pieces

Significant upgrades are currently in progress at our upending site in Aalborg, where Transition Pieces are raised and outfitted. These enhancements are designed to accommodate larger and heavier Transition Pieces.

16 March 2026
Munck.CS.WIND.OFFSHORE3

Expanding our capacity for Transition Pieces

Significant upgrades are currently in progress at our upending site in Aalborg, where Transition Pieces are raised and outfitted. These enhancements are designed to accommodate larger and heavier Transition Pieces.

Key upgrades and benefits include:
-The installation of more than 1,000 new crane mats and extension of the crane tracks, enabling us to upend and outfit more Transition Pieces simultaneously. This includes implementation of a new rainwater drainage system, ensuring optimal working conditions. Enhanced site leveling will improve both safety and efficiency for our teams.

-Installation of new foundation plates engineered to accommodate larger Transition Pieces, aligning with client requirements and evolving market demand for foundations with increased dimensions.

-Expansion of the area, with additional positions prepared for Transition Pieces, resulting in a nearly 25% increase in capacity.

Executing a comprehensive upgrade while maintaining ongoing project operations demands effective coordination.

Through close collaboration with suppliers and the dedicated efforts of our fantastic colleagues at the upending site, everything is coming together successfully.